How Setup Time Sets the Lot Size of a Machined Run
Setup is paid once per lot, so in lots of five to twenty parts the changeover sets the calendar and lot size decides how many parts share it.
What a Setup Contains Before the First Good PartThe study names nine groups of activity that the changeover consisted of, in the order they were done. Removing the fixture from the previous job came first, then study of the clamping sheet and the drawing, cleaning the machine, clamping the new fixture, positioning the zero point, measuring the tools, clamping the tools into the magazine, producing the first piece, and inspecting it.