Every Production article of the Metal CNC Resources, newest first, each written from published standards, research and makers’ data.

The Machined Run

How a machined metal run is sized, timed and released. Setup time sets the lot size, the cycle time is built from the program, one cutting edge makes a countable number of parts, a first article inspection clears the run, and the certificates ship with the lot. The pieces give counts, times and records, never a price.

Cycle Time of a Machined Part From Program to Time per Part

Time per part is cutting, moving, changing and handling plus the lot's share of setup, so check what a quoted cycle time includes before comparing.

What Makes Up the Cycle Time of a Machined PartA CNC program's time has three machine components. Autodesk's help for the machining time tool in its CAM software defines the estimate as the sum of feed time, the time for non-cutting traverse moves at the machine's fastest rate, and tool-change time, and it reports each with its distance and the number of tool changes.

Certificates and Documents That Ship With a Machined Metal Lot

Each document proves something different, so the order names the certificate type, the traceability, the process reports and the inspection data it expects.

The Documents That Travel With a Machined Metal LotA lot of machined metal parts usually travels with four kinds of paper, each issued by a different party and each proving something different. Confusing them is the most common reason a file looks complete and is not.

How Setup Time Sets the Lot Size of a Machined Run

Setup is paid once per lot, so in lots of five to twenty parts the changeover sets the calendar and lot size decides how many parts share it.

What a Setup Contains Before the First Good PartThe study names nine groups of activity that the changeover consisted of, in the order they were done. Removing the fixture from the previous job came first, then study of the clamping sheet and the drawing, cleaning the machine, clamping the new fixture, positioning the zero point, measuring the tools, clamping the tools into the magazine, producing the first piece, and inspecting it.

How Many Parts One Cutting Edge Makes in a Machined Run

The parts an edge makes equal its minutes of life divided by the minutes each part spends on it, so a faster cycle can use more edges than it saves.

What Decides How Many Parts a Cutting Edge Can MakeParts per edge is a quotient. The numerator is the tool life, the minutes a cutting edge can stay in contact with the workpiece before it reaches the wear criterion.

First Article Inspection Before a Machined Metal Run

A machined run ships only after its first article report is approved, so plan the first delivery around the report and not around the last part off the machine.

What a First Article Inspection Does Before a Run ShipsLockheed Martin UK's guidebook gives the purpose in three lines. A first article inspection provides objective evidence that all engineering, design, contractual and specification requirements are correctly understood, accounted for, verified and recorded.

Request a Metal CNC Quote

Send the 2D drawing and the 3D file, with the quantity and the stage of the project. An engineer replies within 1 working day.

The quote form, the mutual NDA and the private folder for your files are on Protolis Atelier, with Metal CNC chosen.

Request a Quote