Meaning
A setup is the work of preparing a machine for one part: fixture, workpiece, zero point, tools, program and first piece. It is paid once per lot, whatever the lot size. A setup also fixes the state the run starts from, so a first article cut on it speaks for the parts that follow. A trial setup measured on its own does not carry that weight.Internal and External Time
The SMED method splits setup work into two kinds. Internal activities happen while the machine stands still, such as changing the fixture, finding the zero point and cutting the first piece. External activities happen while the machine cuts something else, such as finding sheets and measuring tools. The method moves as much as possible from internal to external. Organizational changes alone cut total changeover time by 20 to 30 %, according to the general finding the study cites.Read More
Measured Example
A 2025 study timed a changeover on a five-axis machining center from video. It took 3 hours 26 minutes 32 seconds, of which 1 hour 52 minutes 33 seconds stopped the machine. The longest internal item was the wait for inspection of the first piece. The longest external item was the search for the clamping and program sheet, at 41 minutes 2 seconds. The proposed standard sheet totals 89 minutes, a projection the authors had not yet proved in a long run.Tool Changes
A lot of 50 can run on one setup of tools, while a lot of 1,000 needs a plan for changing them. Each change of edge needs an offset update and a check of the first part after it. A probe is part of the setup as well, including the status of its radio link.Thermal Shift
A setup that was stable on Tuesday can shift on Wednesday when the part program changes. HEIDENHAIN traces that to the screws, which heat according to the mean feed of the program. ISO 286 says nothing about how a part is made. Whether a given machine and tool setup holds an IT grade is a question for the shop.