Meaning
A first article is the first production part measured against every characteristic of the drawing, and its approved report releases the rest of the lot. The part comes from production tooling, production programs and the production process, so it speaks for the run that follows. A part cut on a trial setup and measured on its own does not carry the same weight. The first article inspection (FAI) report is the record of that measurement.Purpose
Lockheed Martin UK’s supplier guidebook gives the purpose in three parts. The inspection shows that every engineering, contractual and specification requirement was understood, verified and recorded. It shows that materials, tooling, processes, documents and people can produce compliant parts consistently. It records that the part is fully compliant, defined, baselined and repeatable. The guidebook adds that the inspected part should not be a qualification unit, since qualification comes before the first article. The report does not measure every part of the lot, and the lot’s own inspection plan covers the rest.Read More
Triggers
A full inspection covers every characteristic, and a partial or delta inspection covers those a change affects. A new part number, a new supplier or a new manufacturing location calls for a full one. A lapse in production of more than 2 years calls for one in the Lockheed, General Dynamics and GKN guides alike. A change of design, process, tooling, material, inspection method or numerical control program calls at least for a partial one. A buyer holding a repeat order for a part last cut three years ago should expect a first article again.Report Forms
The report follows the three forms of AS9102. Form 1 identifies the part, its revisions and whether the inspection is full or partial. Form 2 accounts for materials, special processes and functional tests, with specification revisions and certificate numbers. Form 3 lists each characteristic with its requirement, its measured result and the method and equipment used. A ballooned drawing ties each balloon to a row of Form 3. Anodizing, heat treatment and plating belong on Form 2 with a traceable certificate number. Lockheed rejects a report whose special processor the buyer has not approved. A feature drawn in 12 places needs 12 recorded values, and “accept” or “OK” cannot replace a number.Schedule Effect
Nothing in the lot ships until the buyer approves the report. Lockheed asks for the report no less than 5 working days before the shipment date where no source inspection applies. A rejected report stays rejected until corrective action, a subsequent build and an acceptable delta inspection are complete. For a small order, the first delivery date is therefore the date of the approved report. In an assumed lot of 40 parts, cutting 2 and reporting them before the other 38 limits a late finding to 2 parts. The pause costs machine time, and the guides’ rules explain why it pays.Thermal State
A machining center that changes its work often never settles to one temperature. HEIDENHAIN measured a ball screw growing more than 110 µm (0.0043 in.) in 40 minutes of positioning. The first article therefore carries the machine’s thermal state, and it is cut after a warm-up that matches the production feed. It is measured again after a stretch of the lot. A probe cycle records the datum readings for the first article, so the later parts can be checked against the same reference.Open Questions
The first article is where open questions meet actual metal. Edge sizes, deburring methods and finishes can be confirmed on the first parts instead of argued from notes. A tapped hole that is anodized can be gauged after coating, and a bore with an IT grade can be measured at a stated temperature. In the changeover study of these resources, the first piece waited 58 minutes 26 seconds for inspection. A first-piece check on a priority queue was planned at no more than 10 minutes.