First Article Inspection Before a Machined Metal Run

A machined run ships only after its first article report is approved, so plan the first delivery around the report and not around the last part off the machine.

The first CNC machined aluminum housing of a run on a flat inspection plate, with identical housings from the same run lined up behind it.

A feature that appears in twelve places on a drawing needs twelve measured values in a first article report. Lockheed Martin UK’s supplier guidebook uses exactly that case, a fin to be installed in 12 places, and it says that a single entry does not satisfy it. The same guidebook says the words “accept” or “OK” cannot stand in for a measurement against any note that contains a dimension.

A first article inspection is a document with a physical part behind it, and the order of events matters for a run: the part has to be made, measured, reported and approved before the rest of the lot ships. The notes below set out when a run needs one, what the report contains, how it fits into the sequence of a production run and where reports most often fail. They rest on three supplier guides published by aerospace buyers, each of which describes the process in the buyer’s own terms.

What a First Article Inspection Does Before a Run Ships

Lockheed Martin UK’s guidebook gives the purpose in three lines. A first article inspection provides objective evidence that all engineering, design, contractual and specification requirements are correctly understood, accounted for, verified and recorded. It shows that materials, tooling, processes, documentation and personnel are capable of consistently producing compliant hardware. And it records that the part is 100 % compliant, defined, baselined and repeatable.

One part, or a stated sample, is the unit of evidence, measured against every characteristic on the drawing. Per the guidebook, the hardware used for the inspection has to be part of the first production run and may be part of the first lot of deliverable units. It also says the part should not be a qualification unit, since qualification ordinarily comes before the first article.

For a buyer of machined metal parts, that wording settles the sequence. The first article comes from production tooling, production programs and the production process, so it speaks for the run that follows. A part made on a trial setup and measured separately does not carry the same weight.

A first article is the first piece of the production run, measured against the whole drawing. Its approval is the buyer’s permission for the rest of the lot to ship, in the guides studied here.

What the Report Does Not Do

The report does not measure every part in the lot. It records that the process, once set up, can produce the part, and the lot’s own inspection plan covers the rest. Lockheed’s guidebook says the supplier is expected to have production baseline controls in place to maintain compliance, and to notify the buyer of any change to design, specification, material, component sourcing, production process, facilities or location.

Triggers for a Full and a Partial Inspection

Every characteristic of the part falls under a full inspection. A partial one, also called a delta inspection, covers the characteristics a change affects. The three guides agree in substance, and the table sets them side by side.

Table 1. When a first article inspection is required, as stated in three aerospace buyers’ supplier guides
Trigger Lockheed Martin UK (SQAG 001, Issue 6, Feb 2026) General Dynamics OTS (training, April 2015) GKN Aerospace (guideline, Rev A 2022)
New part number Required for any new part number Full Not stated
New supplier or manufacturing location Required when production moves to a new supplier; a change of source also sits in its partial list Full Full or partial for affected characteristics
Lapse in production Required after a break beyond the contract time or more than 2 years Full after a 2 year lapse Full or partial after a 2 year lapse, citing AS9102
Design change affecting form, fit or function Partial Delta Full or partial
Change in process, tooling, inspection method or material Partial Delta, for a significant change in method Full or partial
Change to the numerical control program Partial Delta Full or partial
Other A natural or man-made event that may harm the process When requested by the buyer Corrective action to complete an earlier incomplete inspection

The 2 year lapse in production appears in the Lockheed guidebook, in the General Dynamics training deck and in the GKN guideline, which cites AS9102. A part ordered again after a long gap is a first article again, and a buyer holding a repeat purchase order for a part last cut three years ago should expect it.

Reading the Wording of a Partial Inspection

A partial inspection is not a shortcut. Lockheed’s guidebook says the requirement, once invoked, continues to apply after initial compliance and that a partial inspection addresses differences between the current configuration and the previously approved one. Only the affected fields in the forms are completed, and the approved configuration is identified in the index of part numbers on the first form. GKN asks for a detailed explanation of the reason for every partial inspection.

The Report in Three Forms and the Package Around It

The report follows AS9102’s three forms. Lockheed’s guidebook describes them as follows: Form 1 identifies the product that is having the inspection, Form 2 accounts for materials, special processes and functional testing, and Form 3 records inspection results for the design characteristics and documents any nonconformances.

Table 2. What each form carries, as described in the supplier guides
Form Name What it records
1 Part Number Accountability Part number and name, serial number, revisions, manufacturing process reference, organization, full or partial inspection and its reason
2 Product Accountability, Materials, Special Processes and Functional Testing Material and process specifications with revision levels, special process suppliers and their codes, certification numbers, functional tests
3 Characteristic Accountability, Verification and Compatibility Evaluation Each characteristic with its number, requirement, measured result, inspection method and equipment

The package around the forms is longer than the forms. General Dynamics OTS lists what each report includes: the three forms, a complete bubbled print, a certificate of conformance, all material certifications, all special process certifications, manufacturing plans, work instructions and process control plans sufficient to document the production process, test documents, a final inspection plan and a picture of part marking. Lockheed asks for a ballooned drawing as part of the package, and allows drawing sheet and zone references as an alternative.

For a machined part, the contents of Form 2 are where a lot’s paperwork is often late. GKN’s guideline asks for copies of the original mill certifications, with no material substitution allowed unless the buyer approves it, and for actual thickness verification of coatings such as anodize and paint.

Assemblies, Bought-In Parts and Special Processes

A machined detail often goes into an assembly, and the guidebook sets rules for the parts around it. For an assembly, every item of the bill of materials, whether detail part, sub-assembly or commercial off-the-shelf item, is listed on the first form. Commercial items need only be stated as standard parts and do not require their own inspection. Where a detail part is bought from a sub-contractor, its inspection is either produced by that sub-tier or covered by a delta inspection of the main contractor.

Special processes bring their own condition. Anodizing, heat treatment, plating and similar steps belong on Form 2 with a traceable certification number, and Lockheed’s guidebook says an unapproved special processor causes the report to be rejected and counts as a part nonconformance. A machined part that leaves the shop for anodizing therefore depends on a second supplier’s approval status before its first article can pass.

Source inspection is a further layer. Lockheed’s guidebook says an inspector at the supplier’s site may re-inspect characteristics on a sample basis or witness the first article, and notification has to come before the inspection is complete. That is a scheduling item for the buyer and the shop to agree before cutting starts.

Where the Inspection Sits in the Run

Once an inspection is required, the calendar of a production run changes. Cutting of the first articles opens the run, and nothing in the lot ships until the report is accepted. The guides state it plainly.

  • Lockheed’s guidebook says the report is reviewed and approved by the buyer’s supplier quality representative before any material shipment, and that material received without an approved report is subject to immediate return.
  • For items that need no source inspection, the guidebook asks for the report no less than 5 working days before the shipment date, and the same period applies to source inspection requests.
  • General Dynamics OTS says the report is submitted before the parts ship and that approval has to arrive before the parts can ship.
  • A report that identifies nonconformances has the status of rejected. In Lockheed’s guidebook, nonconforming product does not go to the buyer without approval from the material review board, such as a buyer-approved waiver.

A lot of ten parts may be the first article itself. When the order is small, the first lot and the first article overlap in time, so the schedule for the run includes the measurement of the first parts, their documentation and the buyer’s review, and the remaining parts wait or run behind them.

Two choices follow for a buyer. One is to accept that the first delivery date is the date of the first approved report, not the date the last part comes off the machine. Another is to split a larger lot so that a first batch carries the first article and the rest follows on approval, which protects the run against a nonconformance found after everything was cut.

For a small run, the first article report and the first delivery are the same event. Plan the date for the report, not for the machining.

When the First Article Fails

Lockheed’s guidebook is exact about the way back from a rejected report. The report stays rejected until the corrective actions for the nonconformance are complete, a subsequent build has been made and an acceptable delta inspection has been completed. Nonconformances are dispositioned and closed out under the supplier’s internal requirements, and the supporting documents join the package.

A subsequent build is a second run of parts, so a failure that needs a changed program or a changed fixture adds a cutting cycle, a measurement and a review to the calendar. General Dynamics’ training deck describes the same arrangement from the other side: a partial inspection is typically completed when a part has been disqualified, to verify that dimensions or attributes rejected earlier now conform.

The consequence for a small run is plain. A part that fails on one characteristic is not corrected by remeasuring the same parts, and the date that matters is the date of the approved delta report.

A Forty-Part Lot Planned Around the Report

Assumed figures show what the choice does. Take a lot of 40 parts, with a cutting cycle of 30 minutes per part, which makes 20 hours of spindle time, and a setup that is ready before the first cut. These numbers are chosen for the arithmetic and belong to no real part.

Table 3. Two ways to schedule the same assumed lot of 40 parts around a first article
Plan Sequence Parts exposed to a late finding Spindle time before the report
A Cut all 40, then measure and report 40 20 h
B Cut 2, measure and report, release the machine for 38 on approval 2 1 h, then a pause for the review

Plan A finishes cutting soonest and carries the whole lot as its risk: a wrong tool offset in the program, a revision mismatch or a feature the program never reached shows up in 40 parts. In plan B the pause costs machine time that sits idle or goes to other work, and in exchange a finding falls on 2 parts. Under the guides’ rules a nonconforming lot cannot ship without the material review board’s approval, so a late finding in plan A holds all 40 parts at once.

For a part that will be reordered, plan B has a second return. An approved report fixes the program revision, the tooling and the measuring equipment, so each later lot starts from a recorded baseline. A later change to any of the three is then a visible trigger, not a quiet drift.

Measurement Evidence Behind Each Balloon

Each balloon on the drawing corresponds to a row in Form 3, and each row needs a measured value, an inspection method and the equipment used. The guides pin down what an inspector looks for.

  1. A number, not a verdict. Lockheed requires a physical measurement for every note that contains a dimension, and lists a visual inspection method used for a dimension among the common documentation errors.
  2. Multiple actuals. A feature required several times, such as the 12 fin positions, requires several recorded values, which can include a range with maximum and minimum.
  3. Equipment capable of the tolerance. Lockheed’s guidebook says equipment accuracy should be at least 10 times the accuracy required and that Gauge Repeatability and Reproducibility studies demonstrate assurance. Where an instrument is rejected, the guidebook says the reviewing engineer lacked confidence that a valid, repeatable and reproducible measurement was obtainable.
  4. Position as a value. GKN’s guideline says coordinate measuring machine data alone is not acceptable for a positional tolerance: the results have to show the actual positional value, and raw data is not acceptable.
  5. Tooling identified. GKN asks for the identification number of designed tooling, or the type of qualified tooling, in the tooling column.

The 10 times rule is Lockheed UK’s own requirement, stated in its guidebook, and other buyers set their own ratios. An order should name the buyer’s rule when one applies, not assume one.

Reasons a Report Comes Back and What They Cost a Run

Lockheed’s guidebook lists the errors that cause rejection, and the list reads as a checklist for any machined parts order. A document that fails review reopens the schedule, because the lot waits on the approval.

  • Missing or incorrect revision levels on the drawing, specifications or special process certificates.
  • Notes with dimensions that carry no measured value.
  • Tolerances read wrongly, such as a three-place decimal dimension that carries plus or minus .010 in the title block, or a basic dimension whose tolerance sits in a feature control frame.
  • Missing certificates of conformance, test reports or sub-tier supplier data, including the wrong material alloy or an incorrect special process.
  • Forms unsigned or undated, and typographical errors in part numbers or inverted numbers in tolerances.
  • Special processors that the buyer has not approved.

None of these is a machining error. Each is a paperwork fault in a document that blocks the shipment of parts that may be good, so a buyer who sees the list can ask a supplier which of them the supplier checks before submitting. A repeat order is a smaller version of the same task, with the previous approved configuration as the baseline.

For a first lot that has to arrive with this evidence, low-volume CNC machining puts the first article at the front of the schedule, and the same report becomes the baseline when the part moves into bridge production.

Sources and Further Reading

Request a Metal CNC Quote

Send the 2D drawing and the 3D file, with the quantity and the stage of the project. An engineer replies within 1 working day.

The quote form, the mutual NDA and the private folder for your files are on Protolis Atelier, with Metal CNC chosen.

Request a Quote